• Installation of a 4-inch diameter API 15 HR x 3.5 km in length fresh waterline. This line traveled from the Chijolito Station to the Chijol D17 Station located in the Pemex Ebano Sector of the Altamira District. Project included complete topographic & boundary surveys and prep. R.O.W., engineering design, material supply, hydrostatic testing and direct-burial on land. Pemex Altamira District, Ebano, Mex., 1997.
• Installation of a 10-inch diameter API 15 HR x 22 km in length fresh waterline. This line traveled from San Diego pig launcher to Tres Hermanos pig receiver in the Pemex Cerro Azul-Naranjos Sector. Project included complete topographic & boundary surveys and prep. R.O.W., engineering design, material supply, hydrostatic testing and direct-burial on land. Pemex Poza Rica District, Naranjos, Mex., 1997.
• Engineering design & construction of an associate-water injection system at the Pemex Campos Arcabus-Culebra Sur Plant, which included supply and installation of a 4-inch diameter API 15 HR pipe (2,000 psi), a pump house, positive-displacement tri-plex pumps, instrumentation, fiber glass storage tanks and sedimentation tanks. Project also included complete topographic & boundary surveys and prep. R.O.W., testing & commissioning as well as horizontal borings & open cuts for numerous road crossings. Pemex Reynosa District, Peña Blanca, Mex., 1998.
• Engineering design & construction of an associate-water injection system at the Pemex Campos Oasis-Corindon-Pandura, which included supply and installation of a 4-inch diameter API 15 HR pipe (2,000 psi), a pump house, positive-displacement tri-plex pumps, instrumentation, fiber glass storage tanks and sedimentation tanks. Project also included complete topographic & boundary surveys and prep. R.O.W., testing & commissioning as well as horizontal borings & open cuts for numerous road crossings. Pemex Reynosa District, Laredo, Mex., 1999.
• Construction of an associate-water injection system at the Pemex Campos Tamaulipas-Constituciones, which included supply and installation of an 8-inch and 3-inch diameter API 15 HR pipes (2,000 psi), a pump house, instrumentation, and electrical sub-stations. Project also included complete topographic & boundary surveys and prep. R.O.W., testing & commissioning. Pemex Altamira District, Altamira, Mex., 1999.
• Installation of a 4-inch diameter API 15 HR x 12.5 km in length crude oil line. This line traveled from Pemex Stations Ocotepec to Acuatempa. Project included complete topographic & boundary surveys and prep. R.O.W., material supply, hydrostatic testing and direct-burial on land. Pemex Poza Rica District, Poza Rica, Mex., 1999.
• Construction of secondary recovery 10-inch and 2-inch diameter API 15 HR x 5.6 km and 7 km waterlines at the Pemex Altamira District. Project included complete topographic & boundary surveys and prep. R.O.W., material supply, hydrostatic testing, direct-burial on land, as well as testing & commissioning. Pemex Altamira District, Altamira, Mex., 2000.